SIAD Industrial Roofing Projects

Please see some examples of completed SIAD Industrial Roofing projects below

Worton Grange
Reading, Berkshire

Project Type
Roof Replacement

Project Client
Crown Interiors

Duration

6 weeks

Roof Size

27,000 ft²

Project Description

For this project the SIAD Industrial Roofing team installed a completely new 27,000 ft² roof, replacing the existing asbestos fibre cement roof with new composite insulated roof panels and skylights.

 

The building was unoccupied for the duration of the works.

Complete Roof Replacement of existing Warehouse from SIAD Industrial Roofing. SIAD Industrial Roofing are part of SIAD Group and offer services such as roof cleaning, roof repair, roof overcladding and complete roof replacement. If a roof has deteriorated to the point that a replacement is often the only viable option, SIAD Industrial Roofing have the experience to safely remove and replace the roof. This option will provide the longest life span for your roof.

Zetica House
Eynsham, Oxfordshire

Project Type
Roof Overclad

Project Client
Zetica Ltd

Duration

5 weeks

Roof Size

16,000 ft²

Project Description

This project involved overcladding an existing asbestos fibre cement roof. Overcladding is the renovation of an existing roof by applying a ‘second skin’ over the top and retaining the roof underneath.

The building was occupied during this project.  Retaining an existing roof reduces disruption during occupation, allowing the building to remain in use.

Complete Roof Replacement of existing Warehouse from SIAD Industrial Roofing. SIAD Industrial Roofing are part of SIAD Group and offer services such as roof cleaning, roof repair, roof overcladding and complete roof replacement. If a roof has deteriorated to the point that a replacement is often the only viable option, SIAD Industrial Roofing have the experience to safely remove and replace the roof. This option will provide the longest life span for your roof.

Avenue 2, Milbrook
Witney, Oxfordshire

Project Type
Roof Overclad

Project Client
Fabulous Bakin' Boys'

Duration

14 weeks

Roof Size

67,500 ft²

Project Description

This project involved overcladding an existing asbestos fibre cement roof while the building was occupied by the tenants.

Overcladding the roof ensured the building remaining fully covered against water ingress and stayed weatherproof while it was in use.